SCREENING MATRIX: Property Use & Redevelopment Potential of Typical Service Stations (Ontario) |
| Tool: | Designed to assist municipalities, property owners, and developers make a preliminary assessment on the redevelopment potential Focuses on how the net site value and municipal site considerations play a role in "creating value" Phase II Environmental Site Assessment is recommended to assist in the decision Click here for a printable PDF version of the Screening Matrix. |
|
Municipal
Site Considerations |
|
||
|
Site has Negative Net Value |
Site has Marginal Net Value |
Site has Positive Net Value |
|
|
Site
is located within a Municipal Community Improvement Plan or revitalization
strategy area |
Redevelopment Potential = Fair |
Redevelopment Potential = Good |
Redevelopment Potential = Very Good |
|
Steps: 1. Engage owner and developer early. 2. Follow framework when project economics
support moving forward. 3. Improve project economics. Consider entire
zone economics, developer incentives, site-specific remediation, etc. |
Steps: 2. Follow Framework to redevelop. 3. Improve project economics through shortened
development time, developer incentives, Community Improvement Plan, flexible
land uses/exit strategies, etc. |
Steps: 2. Follow Framework to redevelop. |
|
|
Site
is located in an area with
redevelopment focus but no firm plans (e.g. Community Improvement Plan) in
place for the area |
Redevelopment Potential = Poor |
Redevelopment Potential = Fair |
Redevelopment Potential = Good |
|
Steps: 1. Engage owner, consultant, regulator and
developer early. 2. Jointly identify redevelopment options and
timeframe. Consider less sensitive interim use and options to improve project
economics. 3. Follow framework when feasible end use
plan is developed. |
Steps: 1. Engage owner, consultant, regulator and
developer early. 2. Jointly identify economically feasible
redevelopment options. 3. Improve project economics through shortened
development time, developer incentives, Community Improvement Plan, flexible
land uses/exit strategies, etc. 4. Follow framework when feasible end use plan
developed. |
Steps: 1.
Engage owner, consultant,
regulator and developer early. 2. Jointly identify economically feasible
redevelopment options. 3. Follow framework when feasible end use plan
developed |
|
|
Site
is located in an area with no plans or redevelopment focus |
Redevelopment Potential = Very Poor |
Redevelopment Potential = Poor |
Redevelopment Potential = Fair |
|
Steps: 1. Framework is NOT applicable.1 2. If desired, develop aesthetics or surface
use agreement with owner, including interim site management obligations. |
Steps: 1. Framework is NOT applicable.1 2. If desired, develop aesthetics or surface
use agreement with owner, including interim site management obligations. |
Steps: 1. Engage owner, consultant, regulator and
developer early. 2. Jointly identify economically feasible
redevelopment options. 3. Follow framework if a feasible end use plan
is identified OR if desired, develop aesthetics or surface use agreement with
owner, including interim site management obligations. |
|

1 Framework is not applicable, please refer to the Brownfields Toolbox, available at www.aboutRemediation.com.
![]() ![]() ![]() |
||
|